Inland Port Infrastructure Improvements


Scenario


Management of a regulated inland port on 600 acres of land determined that physical infrastructure improvements were needed. Engineering working closely with management identified, prioritized and developed detailed project costs.

The total proposed multi-year investment is $2.4 million. The improved infrastructure was viewed as a means to attract additional tenant business and to enhance security measures.

Outcome

Funding
Source

Funds
Obligate

DHS - PSGP

$2.1 million released
$875,000 pending

 



 

Rubin Advisors
$2.1M